Software cost estimation dashboard
Estimate effort, schedule, team size and cost with Basic COCOMO and COCOMO II Post-Architecture, compare both models, read a requirements document into inputs, and export a PDF report. Every number is computed by the Python engine from your inputs.
Saved projects New estimate
| Project | Basic PM | COCOMO II PM | Months | Cost | Actions |
|---|---|---|---|---|---|
| Loading… | |||||
Effort by project (person-months)
The equations
Basic COCOMO
Effort = a × KLOCb
Time = c × Effortd
Staff = Effort / Time
COCOMO II.2000
E = 0.91 + 0.01 × ΣSF
Effort = 2.94 × SizeE × EAF
F = 0.28 + 0.2 × (E − 0.91)
TDEV = 3.67 × PMNSF × SCED% / 100
Effort = a × KLOCb
Time = c × Effortd
Staff = Effort / Time
COCOMO II.2000
E = 0.91 + 0.01 × ΣSF
Effort = 2.94 × SizeE × EAF
F = 0.28 + 0.2 × (E − 0.91)
TDEV = 3.67 × PMNSF × SCED% / 100
Coefficients from Boehm (1981) and the COCOMO II.2000 Model Definition Manual.